Update progress and complete tasks
Start a task, move its progress, tick it off, reopen it, and change several tasks at once.
Les articles d’aide sont pour l’instant en anglais. Le reste de RenovU est dans votre langue.
Progress is a percentage from 0 to 100. It decides the task's status, and the project's overall completion is worked out from it.
Set progress on the board#
- Drag the slider under the task to how far along it is. It moves in steps of 5%.
- Let go. The new figure is saved.
Start a task#
Select Start on a task that's To do, on its row or at the top of its page. It's now In progress, still at 0%, so the board's Status filter and the project's figures count it as under way. Moving a task's progress above 0% starts it too, without selecting Start. Either way, dropping back to 0% leaves it In progress.
To undo a start, select Not started. It shows on a started task while it's at 0%, however it was started.
You can start a task with subtasks too: its progress still comes from them.
Tick off a task#
- Select the round tick at the start of the task's row. The task moves to 100% and drops to the bottom of its room.
- To reopen it, select the tick again. It goes back to 0%.
On the task page, use Mark complete or Reopen at the top.
If the task is waiting on other tasks that aren't finished, RenovU asks Complete anyway? first. If unfinished tasks depend on a task you're reopening, it asks before reopening.
Tasks with subtasks#
A task with subtasks takes its progress from them, so its slider and tick are switched off. Tick off its subtasks instead. When every subtask is done, the task is done too.
Change several tasks at once#
- Select Select above the list. Tick boxes appear on each task.
- Tick the tasks you want, or Select all to take every task shown.
- In the bar that appears, choose Complete, Reopen, Priority…, Move to… (a room), Assign to… or Delete.
- Select Done selecting when you've finished.
If someone else changed one of the selected tasks since your list loaded, nothing is changed and the list refreshes so you can try again.
Hide finished tasks#
Switch off Show completed under the search box to hide tasks that are done. RenovU remembers this for you on this project.
À lire aussi
- Break a task into subtasksSplit a task into smaller steps whose progress adds up to the task's own.
- Make a task wait on anotherAdd dependencies so a task shows as blocked until the work before it is finished.
- Search, filter and sort tasksFind tasks by searching, narrow the board with filters, change the order, and save filters you use often.
- Add and edit tasksAdd a task in one line or with the full form, then change its room, priority, due date, assignees and description.
- Plan the week on a whiteboardMake a whiteboard of this week's or weekend's jobs, tick them off, see what's left to buy, and share it on a phone or a tablet on the wall.
- Add notes, mention people and see a task's historyKeep a running thread of notes on a task, @mention people, and see every change made to it.