See time across the project

Use the project's Time tab to see the total logged, who logged it and which tasks it went on.

Les articles d’aide sont pour l’instant en anglais. Le reste de RenovU est dans votre langue.

The project's Time tab adds up the time logged on all its tasks. Every member can see it.

Open it#

  1. Open the project.
  2. Select the Time tab.

What's on it#

  • The total time logged on the project.
  • By person: each person's total.
  • By task: each task's total.
  • Latest entries: the most recent entries, each with its date, task, person and time. Select a task to go to its Time tab, where entries are changed.

Tasks in the bin aren't counted. If you restore a task, its time comes back into the totals.

When you're looking at a single project on the dashboard, its summary also shows Time logged, linked to this tab.